Tuesday, 17 January 2017

RICA'S evolutions

The CEA express the need to investigate blind cells with a high level of radiation so where human can’t survive. The RICA project is born. It is named RICA for “Robot d’Inspection de Cellule Aveugle” which means blind cells inspection robot. This robot will be modified to cover new needs indeed by the investigation of new cells and different modules to carry. In this article we will review the three previous RICA version which conduct to our project the RICA IV.


RICA I

To create the RICA I the CEA work with CYBERIA to modify “HUGGY” robot and adapt it to the nuclear environment. It also have to be modified to manage the camera and to add a radiation level censor.
The RICA I is divided in two sub-systems: the motorisation and the camera bloc.




A wheel have been added under the camera to ensure a good mobility on flat ground and allow the pilot to take picture of all the blind cells.
This robot have been used in April 2007 in order to examine a cell and especially tanks which contain radioactive products. The RICA I is narrow because for this inspection it was introduce in the cell through a coring.


After this inspection the CEA express new needs. It appears that the wheel under the camera bloc is not enough efficient and the robot have to be more mobile with better crossing capabilities. It was also very difficult to decontaminate the wheels and the coaxial cable. So new technical solutions have to be found.




RICA II

The RICA II is the improved version of the RICA I and take into account feedbacks from previous inspections.
The RICA II is still composed of two sub-systems: the camera bloc and the motorisation. But now the difference is that these two parts are assembled to form a tank.



At the end of 2007 several tests have been done and the RICA II satisfied the new requirements of the CEA.


RICA III

The RICA III is also an evolution of the RICA I and II. You can find a precise description of this robot on our blog, please follow this LINK.

This robot was made because the CEA need to inspect other blind cells with difficult access and because they want to carry more precise camera or a robotic arm.  So the crossing and the transportation capabilities of the RICA II was sufficient.



RICA IV

The RICA III is aging and in operation for more than eight years now so the needs of the CEA have changed and the RICA III performances are not sufficient.
That’s why the CEA request them to improve RICA robot and create the version IV. The first goal is to improve crossing capabilities. The RICA IV have to cross obstacles in step configuration with the following dimensions:




This robot also have to go under an obstacle which is 30 cm from the ground, it have to transport heavy sub-systems (gamma camera, robotic arm, …), these sub-systems need to be easily changed, it can’t weigh more than 100 kg, have to resist from important radiation, the command system have to be improved to be more ergonomic, etc. This robot will be used in a very aggressive place with a lots of constraints which lead to a complex design.


So our work will be difficult for this project and we need robust methods to design this new robot like system engineering and all the expertise of our school.

Friday, 13 January 2017

Toshiba’s dismantling robot :


Toshiba is a Japanese multinational selling electronic components, information technology, power systems or consumer electronic. In 2016, Toshiba is the third biggest world provider of semiconductor, behind Intel and Samsung.
After the Fukushima nuclear disaster in 2011 (more about Fukushima soon), the Japanese government began to look for adapted solutions in order to dismantle the Fukushima nuclear plant.
Fukushima disaster (source: philnews.ph )
One of the hardest task, in order to dismantle this nuclear plant, is removing the 566 fuel rods in the reactor n°3, which is a zone with very high concentrations of radioactivity. Knowing this, Toshiba developed a robot that can float on the surface of the water cooling pool and operate to remove the fuel rods:
Toshiba dismantling robot
This robot can use two robotic arms to collect and cut the remains to allow the third arm to take off all of the 566 fuel rods in the reactor n°3. This robot will be placed this year but it will be operational only in 2018.

More information (including a video): Toshiba invente un robot pour le démantèlement de Fukushima

Thursday, 12 January 2017

Pushing robots


The purpose of this article is to explain the technical choices of the Cooperative robots project (the general article was posted on Wednesday, 23 November 2016 on this blog). According to the first article, the goal of this project was to make 5 sumo robots move together, in front of the main robot, the RICA.


To realize this project, we had at our disposal some specific material :
Firstly, the base of the robot was a Pololu Zumo robot. With this robot, all the parts needed for the locomotion (caterpillars, motors, power source and motor management) were ready to use.

Afficher l'image d'origine

To reach the goal of this project, one of the main challenges was to be able to detect the other robots. To do that, we could use three types of sensors, numeric infrared, analog infrared and analog ultrasonic.
For the detection of the other robots, most of us chose to use analog infrared sensors, because it is easy to use and provides distance informations. Some of us also use ultrasonic sensors to detect obstacles like walls
.
Afficher l'image d'origine


The other aspect of the detection was to make the robot easy to detect by the others, so it was very important to work on the shape of the robot. We choose to build an outer shell with flat sides to make a good surface for sensors. This external shell was made with a 3D printer, because it was an easy way for us to build lightweight parts.  




Finally, to gather the information from sensors, execute the program and command motors, we used a microcontroller Arduino uno. In an upcoming article we’ll see the coding steps.

Afficher l'image d'origine

Wednesday, 11 January 2017

IVTV


    IVTV means Integration Verification Transition and Validation. It is a plan developed and validated during the design step (see picture below) in order to check if the design matches with customer requirements. All stakeholders can refer to this document to see if design models are aligned with the customer's vision and the forecast. This document is also a way to insure a good transmission between teams, activities and processes concerning system design and system realization.




To explain what represent IVTV we can go through each terms:
  • Integration: the purpose is to prepare the system of interest (SOI) for final validation, transition and for production.
  • Verification: the verification process aims to ensure that the system will be built accordingly with customer requirements and will be validated with an acceptable level of risk.
  • Transition: the goal is to ensure that all subsystems can be implemented together or all the interfaces needs are taking into account and managed.
  • Validation: the validation process aims to ensure that the system satisfies the customer and user needs as stated and agreed and ready to be qualified or exploited.


In the IVTV document you will find all these informations:
  • Description of the project
  • Relevant documentation
  • Abbreviations
  • Description of the context: perimeter, constraints, requirements, parameters of the system to be checked
  • Strategy: general principles, actions for integration, verification, transition and validation and schedule of these actions
  • Organization and responsibilities: description of the team, human resources involved, way of working between teams
  • Tools and practical resources (building, warehouse, test bench…)
  • Planning of the design and the production of the system


    It is key to start the IVTV plan as soon as possible. The more early you start the IVTV the more efficient it will be. It is also very important that it is made by other workers to have new points of view. Thanks to this plan we can prove that the design match with the customer requirements. We also minimize the risk of discrepancies between the product and its design.
A good IVTV is obtained after a lot of iterations. A good communication between the different design department and the verification team is also one of the key aspect to ensure an efficient IVTV.

Tuesday, 10 January 2017

Nuclear activities in France


    France started nuclear production in 1956 building the first nuclear reactor “Uranium Naturel Graphite Gaz” (or “UNGG”) in Marcoule.

    It was the beginning of the electronuclear program launched by “Electricité de France” the national provider of electricity in order to ensure a large electricity production.
    After the success of the first UNGG reactor, six reactors were built making electricity production of a unity grown from 70MW (Mega Watt) to 540MW.
    This electronuclear program leaded France as the second world producer of nuclear electricity, even if some major crisis likes the Tchernobyl explosion in 1986 has slowed down the development.
    In fact, France government and E.D.F. had to think about the next generation of nuclear reactor in order to reduce the risk of major crisis, and ensure a bigger electricity production.
    Considering this, France and UE launched the EPR (European Pressured Reactor) between 1990 and 2000.
    The difficulty of this project leaded to important delays (first French reactor should work in 2018 instead of 2012 initially), and the cost is actually of 10.5 billion euros…

Monday, 9 January 2017

OUR FELLOW STUDENTS ARE NOW AWARD WINNERS


On December 14th of 2016 was held the fourth edition of the Dismantling Conferences. There, around 250 professionals discussed the future of the field.
During the morning, several conferences were held. It was the opportunity for guests to show their point of view and their ideas to improve dismantling in general. For example this year they made a round table discussion about the implementation of numeric technologies in the dismantling process and a second one about system engineering integration.
During the afternoon guests would meet other people thanks to a “speed dating-like” organization . Everybody could meet other professionals and make a kind of benchmark. It is an unique opportunity to see what other parties are doing and what their views are for the future of dismantling.
Three awards were given through the meeting. Three apprentices from our promotion are proud to received one. The goal of awarding a trophy to students is to encourage academic training and projects about the dismantling. It is the case of the RICA IV project and the Zumo Robot project we managed early 2016. It was a great opportunity to show to professionals of this field that Mechatronics are relevant and useful for their companies, it may be the start of great collaborations.

DSC00805.JPG

Our three award winning students : Philippe THUILLER, Maxime NAVES and Alexandre MONNY

Friday, 16 December 2016

SE architecture


System engineering use several tools but the most important are architectures.
During the first step of the design we create several architectures of each systems and subsystems. We work on this thanks to a software which allows us to link all aspects of the design (needs, requirements, functions, components...).
The two main architectures are the following:

- Functional architecture

The goal of this architecture is to link all functions of a system and specialy their input and output. So we can justify why each function is needed.  We also see the logic behind our system.


- Organic architecture

The goal of this architecture is to provide a global image of the system components. We can see all links between parts of the system and what their flows are. Thanks to this architecture it will be easier to choose the good component and to implement them together.
We make these kinds of architectures for all system and subsystem but also for the context of our system. It allows us to place our system of interest in its context and see with what it interacts.
So we obtain a complete draw of the system where everything is linked together following the rules below.

These architectures will create new needs and new requirements that are required by the system or forgotten by the customer.
A good architecture is obtained after several iterations to check if anything is forgotten and if everything is coherent and relevant. Then in order to be sure that everything is correct a "verification and validation" step is made by an other team. We will see this aspect of SE in a next article.


Thanks to these architectures we have a precise first design of the system and we can prove that all requirements of the customer are taken into account.